Trutec
Oy

RTA-Metalli Oy (3000 m2)

The steel-framed production hall was implemented quickly and efficiently

Trutec Oy built a production hall and office space for RTA-Metalli Oy in Saarijärvi, covering over 3,000 m2. RTA-Metalli Oy serves its customers as a reliable subcontractor for the metal industry and welding machine shop production. The construction project for the new production facilities and machinery is the largest investment in the company’s history, amounting to approximately 8 million euros.

The steel-framed production hall has a total of 4 bridge cranes with a lifting capacity of 20 tons, which enable the safe handling of long and heavy parts. The hall has welding points and plenty of assembly space.

Trutec Oy took care of the construction project from design to installation.

Trutec Oy was involved in the project right from the design phase.

Trutec Oy was already involved in the project planning phase of RTA Metalli Oy’s new production facility, assembled a cost-effective design team and, in cooperation with the developers, carried out the entire project within the specified overall budget and schedule.

The appearance of the hall has aroused a lot of admiration among passers-by. The premises are functional and we got a hall that was just right for our needs. Our wishes were well taken into account both in the design phase and during construction. “, comments Hanna Auvinen, CEO of RTA-Metalli Oy.

The project was implemented on a tight schedule: installation work began last winter and the doors of the production facility opened in the spring of 2024.

Installation work began in the fall in mid-October and floor work in the hall began in early December. The early arrival of winter brought its own challenges, which were overcome with honor. The project was handed over on May Day -24 and production started by the developers before the summer.

Auvinen has been satisfied with the cooperation: “The hall was erected very quickly and there were no delays. We are really pleased with our new premises.

__wf_reserved_inherit
The project was due to start in October 2023. In the picture, from right, are RTA-Metalli Oy’s CEO Hanna Auvinen, Operations Director Timo Paaananen, and Trutec Oy’s Sales Director Tuomas Anttila.

__wf_reserved_inherit
The walls of the production hall were already erected at the beginning of December 2023.
__wf_reserved_inherit
RTA-Metalli Oy’s production hall in all its glory.

Trutec Oy wishes RTA-Metalli Oy success in its new premises!

Selvitä hallirakentamisen hinta

Haluaisitko tarjouksen juuri sinun tarpeisiisi räätälöidystä hallipaketista?
Tai alustavan hinta-arvion rakennushankkeesi suunnittelua varten?
Ota yhteyttä, palvelemme mielellämme!

Yhteyshenkilösi

Tuomas Anttila
050 400 9057
tuomas.anttila@trutecoy.fi